Project Expansion National Highway 60 - Ben Tre Province

Thursday - 11/07/2024 04:31
Project Name: Investment, Construction, and Upgrading, Expanding 04 Sections from Rach Mieu Bridge to Co Chien Bridge on National Highway 60 (Ben Tre Province) under BOT Contract.
Project Expansion National Highway 60 - Ben Tre Province
  • Investors: Consortium of CII Bridge and Road Investment Joint Stock Company and Khanh An Beverage Trading Joint Stock Company.
  • Project Enterprise: The Rach Mieu Bridge Project - National Highway 60 connecting Tien Giang and Ben Tre Provinces under the BOT Contract.
  • Location:
    • Starting Point: Tan Thach - An Khanh Interchange;
    • Ending Point: Adjacent to the access road to Co Chien Bridge; including 04 sections:
      • Section 1: From Tan Thach - An Khanh Intercommunal Road Interchange to Intersection No. 4, 4.46km long (Expanding the approach road to Rach Mieu Bridge on the Ben Tre side - Phase 1);
      • Section 2: From the end of the road at Ham Luong Bridge to the beginning of Mo Cay Town Bypass, approximately 3.74km long;
      • Section 3: Mo Cay Town Bypass: From the end of Section 2 to the start of the Co Chien Bridge project, approximately 5.80km long;
      • Section 4: Access road to Co Chien Bridge: From the end of Section 3 to the road to Co Chien Bridge, approximately 8.38km long.
    • Total route length: approximately 22.38 km.
  • Total investment capital: VND 1,817.51 billion.

Author: Hưng Lợi Mai